Road work on Parkhaven Boulevard will take place in three phases. Motorists should be prepared for reduced lane widths, loose gravel and curing times during construction.
Phase 1: Saw cutting, median removal and asphalt patching
Phase 1 will include saw cutting, median removal and asphalt patching. This phase is expected to take approximately a week to complete, depending on weather conditions. Drivers are asked to use caution when driving through the area, as lane widths will be reduced during construction.
Phase 2: Oil and chip surface coat
Phase 2 will consist of an oil and chip surface coat. This application helps seal the pavement and provides a base for the final layer of microsurfacing. During this phase, there may be some inconvenience as the materials are placed. With this process, traffic helps roll the rock into the oil, so motorists should expect loose gravel. Once the oil and chips are placed, it will take approximately two weeks before it is cured.
Phase 3 will be the microsurfacing and final surface layer. This material takes approximately three hours to cure before it can be opened to traffic.
This content is sourced from
cityofdanville.org
. It reflects the author's views and has not been edited by our newsroom. It may have been generated using AI assistance.